Kitsap County sets 2026 launch for Harper Estuary restoration
Why it matters
A five-week detour extension keeps a key South Kitsap neighborhood crossing closed through the year-end holidays while awaiting final bridge guardrails.
The big picture
Heavy bridge construction—including seven girders set Sept. 17—progressed on an accelerated 2026 schedule, leaving late-stage roadside hardware as the sole holdup blocking reopening.
By the numbers
770 feet closed between SE Southworth Drive and Inlet Lane SE; 3-foot culvert replaced by a 120-foot bridge; $9,296,000 total funding; extended through Dec. 31, 2026.
Bottom line
Signed detours remain active on SE Southworth Drive and Nokomis Road SE, while Harper Park stays open via Southworth Drive with half its lot fenced for staging.
Go deeper
The bridge completes over 20 years of estuary cleanup following WDFW's 2016–2017 Phase 1 removal of 15,000 cubic yards of historic brick-factory fill.
Drivers, commuters, and pedestrians in South Kitsap face at least five additional weeks of detours around Harper Estuary after county leaders extended the closure of SE Olympiad Drive through December 31, 2026. The Kitsap County Board of Commissioners approved the continuation during its November 23 regular business meeting, citing unforeseen construction material procurement delays in the final stretch of a $9.296 million bridge replacement and salmon restoration project.
The action extends an initial nine-month shutdown that had been authorized under Resolution 013-2026 from February 2 through October 31, 2026 in Commissioner District 2. According to Kitsap Daily News, commissioners acted after supply holdups prevented crews from reopening the crossing on time. County meeting records show roughly 770 feet of SE Olympiad Drive between SE Southworth Drive and Inlet Lane SE remain barricaded, routing vehicles and pedestrians onto SE Southworth Drive and Nokomis Road SE while crews await remaining materials, including guardrails.
Guardrail Supply Delays Push Olympiad Drive Reopening to Year-End
The November 23 decision, filed under Agenda Item 163/2026 by Kitsap County Public Works Roads staff, authorizes a continuation of the temporary road closure first adopted under Resolution 013-2026. That original order shut down the 770-foot roadway segment across Section 2, Township 23 North, Range 2 East, Willamette Meridian from February 2 through October 31, 2026, establishing a roughly nine-month construction window to remove an undersized culvert and build a clear-span estuary bridge.
Although major structural assembly moved forward through the summer and early autumn, delivery bottlenecks for finished roadside hardware stalled the planned fall reopening past October 31. On its Harper Estuary project page, the Kitsap County Department of Community Development noted in a November 2026 update that construction has reached its final phases of completion but requires the extended shutdown specifically because of material delays, including delays in receiving guardrails.
County fiscal documents attached to the November 23 resolution specify that the continuation imposes no net financial impact beyond minimal staff administration under Public Works contact Anthony Burgess and Public Works Roads Director Christopher Piercy. Legally grounded in Washington road closure statutes RCW 47.48.010 and RCW 47.48.020, the resolution sets an upper closure boundary of up to but not exceeding December 31, 2026, while directing the County Engineer to complete public advertising and roadway posting as required by state law across the South Kitsap construction zone.
How a Nine-Month Schedule Shifted From Late Fall to December 31
Comparing three official county timelines from late 2025 through November 2026 shows how an accelerated winter launch eventually encountered late-stage supply chain friction. When the Board of Commissioners first awarded the construction contract to Scarsella Bros., Inc. on December 8, 2025, a county announcement projected bridge construction from June 2026 through January 2027, with overall project wrap-up targeted for April 2027.
Just over a month later, county engineers advanced the start by four months. In a January 26, 2026 bulletin, Kitsap County reported that contractor availability and alignment with Washington's permitted in-water fish window allowed crews to mobilize on February 2, 2026, pulling expected completion into late fall 2026. Crews performed nighttime low-tide work from February 12 through February 25 before shifting to weekday shifts from 6 a.m. to 6 p.m. and hosting a February 24 community meeting at Colby United Methodist Church in Port Orchard.
Major structural erection stayed aligned with that accelerated calendar into September. Kitsap Daily News reported in September that crews scheduled delivery and placement of all seven bridge girders on September 17 at roughly one-hour intervals between 7 a.m. and 2 p.m., using single-lane alternating traffic control and 15-minute ferry-prioritized holds on SE Southworth Drive while recommending Banner Road SE and State Route 160 as an alternate ferry corridor. Heavy span placement finished well ahead of winter, leaving guardrail procurement as the narrow bottleneck holding the road shut.
What Engineers Built Across the 640-Acre Harper Creek Watershed
Beneath the road detours, the construction removes one of South Kitsap's persistent tidal barriers within the 640-acre Harper Creek watershed and its two miles of stream habitat. For decades, SE Olympiad Drive crossed the pocket estuary over an undersized three-foot culvert that constricted saltwater exchange and blocked migrating fish from reaching sheltered estuarine waters and upstream rearing habitat.
According to a January 2025 engineering briefing by Capital Projects Manager Michele Filley, the replacement crossing carries a 122-foot span in design slides, summarized in county public notices as a 120-foot bridge. Because the new structure clears the tidal channel rather than burying it beneath compacted road fill, bridge abutments stand six to ten feet higher than the former road grade, supporting two 10-foot travel lanes, five-foot shoulders, and 3.5-foot railings while improving flood resiliency.
County and state planners selected the 120-foot bridge alignment alongside the Washington Department of Fish and Wildlife after evaluating structural alternatives starting in 2016 and aligning the span with state fish-passage standards under Washington Administrative Code 220-660 alongside neighborhood input. Under the final bid specifications, the crossing adds refined stormwater treatment, a six-foot-wide ADA-compliant pedestrian access ramp with a load and unload area, and a small watercraft hand-launch on the northeast side of the bridge. Roadway approaches pair 10-foot travel lanes with 10-foot shoulders split evenly between asphalt and gravel behind the pending guardrail assemblies.
Why County Staff Rejected Keeping One Lane Open Through Construction
Before asking commissioners to extend the closure past October 31, county staff reviewed whether contractors could reopen a partial travel lane on SE Olympiad Drive while finishing the bridge approaches and roadside hardware. Project managers evaluated the potential effects on both everyday commuters and emergency responders before advising the board to keep the full 770-foot corridor closed through year-end.
According to the November 23 agenda packet, Kitsap County's project team reached three specific conclusions against allowing traffic through the active site during construction activities. Staff determined that opening the work zone to motorists or pedestrians would lengthen the duration of construction, cause additional delays to the public, and create a more hazardous work zone carrying unneeded risk for travelers. With bridge abutments rising six to ten feet above the prior road elevation and guardrails still missing along the shoulders, the unfinished bridge deck cannot safely carry mixed public traffic.
Keeping the total shutdown in place represents an intentional operational trade-off as winter darkness arrives earlier and seasonal storms push higher tides into Puget Sound pocket estuaries. By keeping through traffic diverted onto SE Southworth Drive and Nokomis Road SE while guaranteeing direct driveway access for adjacent properties and uninterrupted passage for emergency vehicles, Public Works separated active construction crews from live traffic without running alternating flagger queues across an unguarded bridge deck.
From Early 1900s Brickworks to a $9.296 Million Restoration Package
The Olympiad Drive span closes the final chapter of a restoration effort shaped by more than a century of industrial fill and over two decades of multi-agency planning. Following U.S. Army Corps of Engineers interest in 2002, a 2006 feasibility grant to the Mid-Sound Fisheries Enhancement Group, and a 2012 Puget Sound Nearshore Ecosystem Restoration Project priority ranking, the Washington Department of Ecology selected Harper Estuary in 2013 for Natural Resource Damage settlement funds from Tacoma's former ASARCO smelter.
According to a 2016 project report prepared by Kitsap County and the Washington Department of Fish and Wildlife, an early 1900s brick factory near today's Harper Park ballfield was demolished in the 1940s, with clinker bricks and debris pushed into the marsh. Phase 1 work in 2016 and 2017 removed roughly 15,000 cubic yards of industrial fill containing slightly elevated arsenic and cPAHs, cleared a fill-dirt boat landing and concrete bulkhead, and replaced a second restrictive culvert under SE Southworth Drive with a 16-foot box culvert.
Project funding also scaled up between early 2025 planning and contract award. January 2025 county slides listed an $8.5 million construction estimate combining $5.9 million in federal PROTECT funds and $2.5 million from a Navy Resilience Fund grant, whereas the December 2025 contract award and November 2026 fiscal summary report $9,296,000 secured across $6,840,000 from the federal PROTECT Program, $1,456,000 from the state Brian Abbott Fish Barrier Removal Board, and $1,000,000 in Kitsap County REET 2 funds.
What South Kitsap Drivers and Harper Park Visitors Should Expect
Until Scarsella Bros., Inc. receives and installs the delayed guardrails and Public Works clears the crossing for striping and final inspection, SE Olympiad Drive remains barricaded between SE Southworth Drive and Inlet Lane SE for all vehicles and pedestrians. Signed detours continue routing neighborhood commuters and Southworth-area drivers onto SE Southworth Drive and Nokomis Road SE, with county outreach continuing through completion.
Visitors heading to Harper Park at 3500 SE Southworth Drive, located roughly two miles from the Sedgwick Road exit off State Route 16, can still access the park entrance, non-motorized boat launch, ball field, trails, and picnic shelter from SE Southworth Drive. However, half of the park parking lot remains enclosed by temporary fencing as a contractor staging yard, and county planners established during Phase 1 design that trailerable boat access would not return after restoration in favor of pedestrian and hand-launch shoreline access. Standard weekday work continues from 6 a.m. to 6 p.m., with resident inquiries handled through Kitsap1 at 360-337-5777 and GovDelivery alerts.
At contract award in December 2025, Commissioner Oran Root noted that more than 20 years of planning and community engagement went into restoring the estuary while preserving neighborhood access. Even with the five-week extension, reopening by December 31 still beats the county's original January 2027 bridge target, restoring full tidal exchange for juvenile Chinook salmon and Puget Sound marine life.